Project scheduling software (scriptable, cross-platform, and open source)
GanttPV Home
Why GanttPV? Help Scripts Server Developer Object Role Modeling
Forum

Set Plan Bar Color By Dependency

Status

in v0.8

Description

Set the colors of all

How to Use

Select tasks. Run script. Selected tasks will be changed to green. Prerequisites and successors to those tasks are colored. The colors from prerequistes to successors are: Orange - Yellow - Green - Blue - Indigo.

How It Works

Colors are set in this order:
1- All rows are set to the default color
2- Second prerequisites are set to orange
3- Second successors are set to indigo
4- Direct prerequisites are set to yellow
5- Direct successors are set to blue
6- Selected tasks are set to green

Critique

Any manually set colors are lost.

Contributors

Brian