Set Plan Bar Color By Float

Status

in v0.8

Description

Sets task bar color based on the available float time

How to Use

Optionally select rows. If no rows are selected, all will be changed. Run script. Task bar colors are changed based on the amount of float. The colors are in rainbow sequence and are based on multiples of the chart time period.

How It Works

The interval used to color plan bars depends on the gantt chart period. If the float is zero, the color is set to red. Otherwise the color depends on the multiple of periods. The colors sequence is: red (0 hours), orange (1 period), yellow (2 periods), green (3 periods), blue (4 periods), indigo (5 periods), violet (greater than 5 periods).

Contributors

Brian